How many operators you need, and how evenly the work is spread.
Opens the editor with one process per station (work time as C/T). Add P/T there to see PCE. No account needed.
Enter the work time at each station and your takt. It shows the number of operators needed (total work time ÷ takt, rounded up), each station's utilisation against takt, and the balance efficiency of the line.
A balanced line gives every station about the same work, close to takt. Balance efficiency is the share of capacity not wasted waiting on the slowest station; anything below 100% is idle time you could rebalance. A bar above the takt line cannot keep up with demand.
Operators needed = ⌈ total work time ÷ takt ⌉ Utilisation = station work time ÷ takt Balance efficiency = total work time ÷ (stations × longest station) × 100
Stations of 40, 50 and 60 s at a takt of 60 s: total work = 150 s, so operators needed = ⌈150 ÷ 60⌉ = 3. Balance efficiency = 150 ÷ (3 × 60) = 83.3%, and station 3 is the bottleneck.
You cannot staff a fraction of a person. 2.5 operators of work needs three people, which is also why a line can look 'balanced' on paper yet still carry idle time.
A stacked bar chart of each station's work time against the takt line. It shows at a glance which stations are overloaded and where work could move.
The hands-on work per unit at that station, including any walking and handling that is part of the job. Use the same unit for every station.