Step Ladder (Time Ladder) Calculator

See lead time, value-add time and PCE for a chain of steps.

Time ladder lead time · VA time · PCE
1
sec
sec
Wait before Weld
pcs
2Above takt
sec
sec
Wait before Paint
pcs
3
sec
sec
Wait before Pack
pcs
4
sec
sec
units

Takt = 58.7 s per unit — used to flag slow steps and to turn pieces waiting into time (wait = inventory × takt).

Lead time
4.3 h
VA time
2.7 min
PCE
1.0%
Above takt
1 of 4
steps slower than takt

Waiting makes up 98.7% of lead time. Shortening waits usually beats speeding up the work.

40s55s30s35sCut2.0hWeld1.3hPaint58.7mPack
Value-add (P/T) Wait Step above takt

Opens the editor with these steps, waits and takt as a ready-to-edit map. No account needed.

What it calculates

The time ladder lines up your steps from left to right. Raised plateaus are value-add time (P/T); the flat sections between them are waiting. It totals lead time, value-add time and process cycle efficiency (PCE = value-add time ÷ lead time).

What it means

Most of the time a product spends in a process is waiting, not being worked on, which is why PCE is usually small. A ladder with long flat sections tells you where the stock is piling up; shortening those waits is usually a faster win than speeding up the work itself.

The formula

VA time = sum of P/T
Lead time = sum of C/T + sum of waits
Wait = inventory × takt   (Little's Law)
PCE = VA time ÷ lead time × 100

Worked example

Three steps with C/T 45, 70 and 50 s and P/T 40, 55 and 30 s, with 120 and 80 pieces waiting between them at a takt of 58.7 s: waits total 200 × 58.7 = 11,739 s, lead time = 165 + 11,739 ≈ 11,904 s (3.3 h), VA time = 125 s, so PCE ≈ 1.1%.

Common questions

What is a good PCE?

Single-digit PCE is common in value streams that have never been mapped, because waiting dominates. Treat it as a trend to improve, not a pass mark: the same map redrawn after a kaizen should show it rising.

What is the difference between C/T and P/T?

P/T (process time) is the hands-on, value-adding time for one unit. C/T (cycle time) is how often a unit leaves the step, so it also includes time lost to waiting for parts, adjustments or handling.

How is the wait between steps worked out?

Inventory × takt. If 120 pieces are queued and one is consumed every 58.7 seconds, the last one waits about two hours. You can also type the wait in directly.

Take it from a number to a map.

PruneChart draws the whole value stream, flags every step slower than takt in red, and works out lead time and PCE as you build.