Availability × performance × quality for a machine or line.
Between the typical 60% and the commonly quoted 85% world-class benchmark.
Opens a blank map in the editor. No account needed.
OEE multiplies three factors: availability (the share of planned time the machine ran), performance (how fast it ran compared with its ideal cycle time) and quality (the share of parts that were good first time).
OEE shows how much of your planned time produced good parts at full speed. The three factors also tell you where the loss is: downtime hits availability, slow running or short stops hit performance, and scrap and rework hit quality. 85% is commonly quoted as world-class, while many plants sit nearer 60%.
Availability = run time ÷ planned production time Performance = (ideal cycle time × total units) ÷ run time Quality = good units ÷ total units OEE = availability × performance × quality
480 minutes planned with 60 minutes of downtime gives 420 minutes of run time (availability 87.5%). At an ideal 30 s per unit, 780 units in 420 minutes gives performance 92.9%. 741 good units gives quality 95%. OEE = 0.875 × 0.929 × 0.95 ≈ 77.2%.
The fastest cycle time the machine can sustain for good parts — from the manufacturer's rating or your best proven run, not your average.
Making more than the ideal rate allows means the ideal cycle time is set too slow or the counts are wrong. The calculator caps performance at 100% and tells you rather than inflating OEE.
PruneChart's suggested OEE field is the simpler uptime × yield. This calculator is the standard three-factor OEE, which also accounts for running slower than ideal.
PruneChart draws the whole value stream, flags every step slower than takt in red, and works out lead time and PCE as you build.