Solve for lead time, work in progress or throughput.
Opens a blank map in the editor. No account needed.
Little's Law links three numbers that describe any steady flow: work in progress (WIP), throughput and lead time. Enter any two and the third is solved: lead time = WIP ÷ throughput.
The more stock sitting in a process, the longer each unit waits — even when nobody is working any slower. This is why cutting WIP shortens lead time, and it is the reason a value stream map computes wait time as inventory × takt.
Lead time = WIP ÷ throughput WIP = throughput × lead time Throughput = WIP ÷ lead time
A process holds 100 units and ships 20 units per hour. Lead time = 100 ÷ 20 = 5 hours. Halve the WIP to 50 and, at the same throughput, lead time falls to 2.5 hours.
Yes, as long as throughput and lead time use the same one. If throughput is units per hour, lead time comes out in hours.
It holds for long-run averages of a stable process, where what goes in roughly equals what comes out. It does not predict the lead time of one particular unit.
Throughput at the pace of the customer is 1 ÷ takt. That is why the wait caused by an inventory triangle on a value stream map is inventory × takt.
PruneChart draws the whole value stream, flags every step slower than takt in red, and works out lead time and PCE as you build.