Takt Time Calculator

The pace your customer buys at, per shift, per week or per batch.

Takt time seconds per unit
Net of breaks, meetings and planned maintenance.
units
Takt58.7 sec/unit
  • = 58.7 s per unit
  • Any process with a C/T above this cannot keep up with demand.

Opens the editor with this takt set, ready to map. Any step slower than it turns red. No account needed.

Weekly + Batch input layouts adapted from: J Mah, J. Takt Time Calculator. Available at: omnicalculator.com/other/takt-time. Accessed: May 26, 2026.

What it calculates

Takt time is the available production time divided by customer demand — the number of seconds you have to make each unit if you are to keep up with what customers actually buy.

What it means

Takt is the pace of the whole value stream. Any process whose cycle time (C/T) is longer than takt cannot keep up with demand, so it becomes the bottleneck. In PruneChart those steps are flagged red automatically.

The formula

Takt time = available production time ÷ customer demand
Weekly: net time = (hours per day − breaks) × days per week

Worked example

A shift of 7.5 hours is 27,000 seconds. If customers need 460 units per shift, takt = 27,000 ÷ 460 = 58.7 seconds per unit.

Common questions

What should I count as available time?

The time the line can genuinely produce: subtract lunch, breaks, meetings and planned maintenance from the shift length. Using the full shift overstates your capacity and gives a takt that is too slow.

What if a process's cycle time is longer than takt?

That step cannot meet demand on its own. You can reduce its cycle time, split the work across more people or machines, rebalance work from the slow step to its neighbours, or add capacity such as overtime.

How is takt time different from cycle time?

Takt is set by the customer: how fast you need to produce. Cycle time is set by your process: how fast you actually produce. Lean aims to bring cycle time to just under takt.